It was determined towards the end of construction that certain plasterboard walls did not meet the required Fire Rating Level (FRL) and needed to be increased to an FRL of – /60/60.
The CAP508 system with its 60 minute performance on standard plasterboard surfaces offered an efficient, cost effective solution that allowed the newly installed plasterboard linings to remain.
The client achieved the required level of fire rating with minimal disruption. With the CAP Coatings airless spray application the high level of finish required for the apartments fit out was not compromised and the project was able to remain on schedule for completion.